How Much Does it Cost to Upgrade to 200 Amp Panel?

A 100 Amp to 200 Amp electrical panel upgrade in Ontario typically costs $2,500 to $5,000, with some projects costing more when utility work, underground service, panel relocation or other upgrades are involved.

For homeowners in Toronto and the GTA, we recommend treating that as a planning range rather than a fixed price.

Why?

Because the breaker panel in your basement is only one part of a 200 amp service upgrade.

The electrician may also need to deal with the meter base, service conductors, grounding and bonding, the connection to the utility and, in some homes, the overhead mast or underground service equipment.

That is why two houses that appear almost identical can receive very different quotes.

Here is what actually changes the price.

xb-200amp-panel-cost-ontario

How Much Does 100 Amp to 200 Amp Upgrade Cost in Ontario?

Based on the residential service upgrades we quote and the type of work involved, these are reasonable amounts to use when budgeting:

Type of workTypical planning range
100 A panel replacement, same service size$1,800–$3,000
100 A to 200 A service upgrade$2,500–$4,500
100 A to 200 A service upgrade in the GTA$3,000–$5,000
60 A to 200 A upgrade$3,500–$5,500
More complex underground 200 A upgrade$4,000–$6,500+
200 A to 400 A service upgradeFrom ~$4,000–$6,500+

These numbers should be treated as budgeting estimates, not universal Ontario pricing. A straightforward overhead service upgrade and an underground installation requiring utility or civil work are not the same job.

What Does XB Electric Charge for a 200 Amp Upgrade?

At XB Electric, our typical pricing is:

XB Electric typical pricing

Panel replacement~$3,000
200 amp service upgrade~$3,500
Typical service-upgrade range (straightforward installations)~$2,500–$3,500

The final number depends on the existing electrical service and what has to be changed to safely supply 200 amps. Before you commit to the work, we identify the major items affecting the quote so you understand what you're paying for.

What Is Actually Included in a 200 Amp Service Upgrade?

This is where homeowners sometimes get confused. A panel replacement and a service upgrade are not necessarily the same thing.

If we replace an old 100 amp panel with another 100 amp panel, the electrical service feeding the house may remain unchanged. Going from 100 amps to 200 amps can involve considerably more.

Depending on the property, the job may include:

  • a new 200 amp breaker panel and breakers
  • new service entrance conductors
  • a 200 amp-rated meter base
  • grounding and bonding upgrades
  • changes to the service mast or attachment point
  • utility coordination
  • ESA notification and inspection
  • identification and correction of deficiencies related to the work
  • circuit identification and panel labelling

The exact scope depends on the existing installation and the requirements of the local electricity distributor.

How Much Is the ESA Permit for a Panel Upgrade in 2026?

Here's an important correction to a lot of outdated information online.

$92 As of April 1, 2026, ESA's minimum inspection notification fee is $92.

ESA's 2026 Residential Fees Quick Reference Guide lists contractor pricing of $86 for a residential new service, service change, panel change or service repair, but that amount is subject to the $92 minimum notification fee when the total notification would otherwise fall below the minimum. The actual notification charge can be higher if additional work is included.

So if a contractor's quote contains more than $92 under a broad heading such as permits, inspections or administration, don't automatically assume you're being overcharged. Ask what the amount includes.

Do You Need an ESA Notification for a Panel Upgrade?

Yes.

Electrical installation work in Ontario must comply with the Ontario Electrical Safety Code, and notification requirements apply to this type of service work.

When you hire someone to perform electrical work in your home, use a Licensed Electrical Contractor. ESA states that Licensed Electrical Contractors are the businesses legally authorized to perform electrical work for hire in Ontario, subject to specific exemptions.

After the work has been reviewed and accepted, ESA issues a Certificate of Acceptance. ESA specifically recommends keeping this document and notes its importance for insurance and resale purposes.

At XB Electric, we coordinate the ESA notification and the required utility steps as part of the service-upgrade process.

How Long Does a 200 Amp Service Upgrade Take?

There are really two answers.

The electrical work itself can often be completed in one working day for a straightforward residential upgrade. The complete project, including utility coordination and inspection requirements, can take longer. That's an important distinction.

Toronto Hydro, for example, states that it will contact a customer within 10 business days during its review process. For projects requiring design and an estimate, its Job Quotation or Offer to Connect stage can take up to 60 days once all required information has been received. Simple projects may move considerably faster.

Once all required inspections and service conditions have been satisfied, Toronto Hydro says the actual service upgrade for installations of 750 V or less is generally scheduled within approximately five business days.

So rather than promising "1–3 weeks," we tell homeowners: The physical upgrade is usually the short part. Utility scheduling determines much of the overall timeline.

Do You Need to Rewire the House When Upgrading to 200 Amps?

Usually not.

A service upgrade does not automatically mean every branch circuit in the house has to be replaced. The wires feeding existing lights, receptacles and appliances may remain in service if they're suitable and the installation can be safely connected to the new equipment.

Older homes, however, deserve a closer look. Knob-and-tube wiring, aluminum branch wiring, damaged conductors, improper alterations or other deficiencies can affect the scope of the job.

Don't assume that because a house was built in the 1950s or 1960s it needs a complete rewire. And don't assume everything can simply be reconnected without looking at it either. The electrician needs to evaluate the installation that is actually there.

Should You Replace a 50-Year-Old Electrical Panel?

Not simply because it turned 50.

Panel age matters, but condition matters more.

We become more concerned when we find things such as:

  • signs of overheating
  • corrosion or water damage
  • damaged breakers or bus components
  • loose connections
  • repeated unexplained breaker trips
  • inadequate capacity for planned loads
  • obsolete equipment for which suitable parts are difficult to obtain
  • alterations that have compromised the installation

A fuse panel is not automatically dangerous simply because it uses fuses. The problem is often that the electrical system is old, has limited capacity or has been modified repeatedly over several decades.

If you smell burning, hear persistent arcing or buzzing, see evidence of overheating, or notice other signs of an electrical fault, that isn't a "plan an upgrade sometime this year" issue. Turn the situation over to a qualified electrical professional promptly.

Do I Need 200 Amp Service for an EV Charger?

Not necessarily.

This is one of the most common reasons homeowners call us about service upgrades, and it's also one of the situations where a 200 amp upgrade can sometimes be avoided.

Depending on the existing load, the home may be able to support an EV charger at an appropriate output without increasing the service size. Energy management is another possibility.

So before spending several thousand dollars increasing the service solely because you bought an EV, have the electrical load assessed first. We've covered that separately in our Is 100 Amp Service Enough for an EV Charger? guide.

On the other hand, if the EV is only one part of a larger electrification plan—perhaps you're also installing a heat pump, induction range, hot tub or second EV—a 200 amp service starts making much more sense.

When Is a 200 Amp Upgrade Worth It?

Think beyond the next appliance.

A 200 amp service becomes especially attractive when you're planning several major electrical loads, such as:

An EV chargerParticularly when combined with other large loads.
A heat pump or electric heating equipmentThe actual electrical demand varies significantly by system.
A hot tub or sauna
An induction range or additional electric appliances
A basement apartment or additional dwelling unit
A major addition or renovation
A second EV
The point isn't that every home with these features needs 200 amps. The point is that once several large loads are being added, it makes sense to evaluate the service as a whole rather than solving each project separately.

Are There Ontario Rebates for a 200 Amp Panel Upgrade?

There is not currently a standalone electrical-panel-upgrade rebate listed under Ontario's Home Renovation Savings program. The distinction matters.

The program does currently provide incentives for qualifying improvements including cold-climate air-source heat pumps, ground-source heat pumps, smart thermostats, solar and battery storage, insulation and certain appliances.

As of August 2026, Save on Energy lists incentives including:

Eligible upgradeCurrent advertised incentive
Cold-climate air-source heat pumpUp to $7,500
Ground-source heat pumpUp to $12,000
Solar panels and battery storageUp to $10,000
Smart thermostat$100
Eligible appliancesUp to $200
Attic insulation$1,250

Eligibility requirements and program terms apply, and heat-pump rebate amounts depend on the equipment installed.

So the panel itself may not qualify for a rebate, while the project that creates the need for more electrical capacity may qualify. That's a much more accurate way to explain it.

And because incentive programs change, always confirm eligibility before buying equipment.